Local Highways Maintenance Transparency Report 2026-2027

Maintenance Plans and Spending

Spending on highways maintenance

Types of work, 2024-25, 2035-26 then 2026-27 projected
Types of work 2024-25 2025-26 2026-27 Projected
Total spend on highways maintenance £17,891,028 £21,501,840 £25,950,066
Of which spent on: - - -
Carriageways £6,406,981 £7,688,988 £11,560,543
Footways £3,620,341 £5,632,052 £5,542,750
Structures (for example bridges or tunnels) £334,420 £1,760,402 £51,800*
Drainage £131,150 £267,363 £370,150
Street lighting £1,366,027 £1,534,055 £1,348,500
Other assets £6,023,418 £4,619,201 £7,076,323

*£2.4m for structures is subject to a viable business case for capital funding which is currently being prepared.

Where our funding for highways maintenance comes from

Funding sources for highway maintenance, 2024-25, 2035-26 then 2026-27 projected
Funding sources for highways maintenance 2024-25 2025- 26 2026-27 (projected)
Funding received through the Department for Transport / UK Government £8,151,000 £8,805,000 £11,083,000
Additional highways maintenance funding provided by the Council or third parties £9,740,028 £12,696,840 £14,567,096
Total £17,891,028 £21,501,840 £25,650,096

Our maintenance plans for this year

Our plans for highways maintenance for 2026-27

Type of works, task name and then length
Type of works Task name Length (km)
Carriageway Preservation Treatment Royal Artillery Way 3.30
Carriageway Resurfacing Manners Way 1.17
Carriageway Resurfacing Sutton Road 0.85
Carriageway Resurfacing Eastern Ave 0.55
Carriageway Resurfacing Hamlet Court Road 0.71
Carriageway Resurfacing Eastwoodbury Lane 0.85
Carriageway Resurfacing Woodside 0.50
Carriageway Resurfacing A13 London Road 0.40
Carriageway Resurfacing A13 London Road 0.65
Carriageway Resurfacing Thorpe Hall Avenue 0.82
Footway Resurfacing Ailsa Road 0.45
Footway Resurfacing Earls Hall Avenue 1.34
Footway Resurfacing Lymington Avenue 1.25
Footway Resurfacing Ashburnham Road 0.69
Footway Resurfacing Woodgrange Drive 1.80
Footway Resurfacing Milton Road 0.85
Footway Resurfacing Canewdon Road 1.32
Footway Resurfacing Elmsleigh Drive 1.27
Footway Resurfacing Dandies Drive 0.70
Footway Resurfacing Green Lane 0.54
Footway Resurfacing Wentworth Road 1.17
Footway Resurfacing Chalkwell Park Drive 1.03
Footway Resurfacing Rectory Grove 0.74
Footway Resurfacing North Crescent 1.59
Footway Resurfacing Feeches Road 0.29
Footway Resurfacing Norwich Avenue 0.63
Structures Gypsy Bridge -
Coastal Three Shells Lagoon -
Cliff stability Belton Way -
Road safety New Road -
Road Safety Woodgrange Road -
AWINEP Woodgrange Road -
AWINE Thorpe Hall Avenue -
Major infrastructure Better Queensway -
Major infrastructure Seaway Car Park -
Major infrastructure Marine Parade -
Major infrastructure Leigh Port -

Full list of planned carriageway and footway works

Carriageway and footway maintenance works are published as part of our Highways Improvement Programme pages. These are categorised under Wards to enable the public to look at roads most relevant to them in a clear and accessible way. Highways Improvement Programme 2026 to 2027 – Highways Improvement Programme – Southend-on-Sea City Council.

How decisions are made on our maintenance plans

Southend uses the recommendations of the national 'Codes of Practice for Highways, Well- managed Highway Infrastructure' to prioritise highways maintenance requirements. Southend undertakes a 100% network coverage condition survey every year for both roads and footways.

We ensure both risk and condition are considered in our decisions and scheme selection process.

We have developed a Priority listing for all roads and footways. This is based on:

  • condition data
  • a risk score, derived from a strategic and operational risk assessment

These elements are combined, along with additional information including:

  • numbers of previous repairs
  • numbers of reported potholes
  • for footways, the number of street trees on the road

This gives us a Priority score. We use this to develop a 5-year programme. We are currently delivering year 3 of this programme.

We would like to extend this programme, however, future requirements aligned to Local Government Reorganisation (LGR) must be considered.