Local Highway Maintenance Transparency Report

Our highway network

Our network is made up of:

  • roads
  • pavements
  • cycleways
  • other public right of way
Use the first column for road type, moving right for the lenght in kilometres (Km))
Type of road Length in kilometres (Km)
A roads 33.9
B and C roads 44.3
U roads 379.1
Total roads 457.3
Pavements (footways) 874
Cycleways 41.8
Other public rights of way 46.9

We have shared this information with the Department for Transport (DfT).

For more information on the different types of roads, visit the GOV.UK website.

We are also responsible for a number of other key assets including:

  • 172 structures and bridges
  • 15265 streetlights
  • 1777 lit up signs
  • 680 traffic signals
  • 23467 road drains (gullies)
  • 11833 road signs

Highways maintenance spending figures

This table shows our current and past spending to maintain our highways.

Preventative works are long lasting. They aim to limit the need for regular repairs. Whereas reactive works are completed as and when needed.

Use the first column for financial year, moving right for capital allocated by DfT, Capital spend, estimated percentage spend on preventative maintenance, and finally, estimated percentage spend on reactive maintenance.
Financial Year Capital allocated by DfT (£) Capital spend (£) Revenue spend (£) Estimate of percentage spent on preventative maintenance Estimate of percentage spent on reactive maintenance
2025 to 2026 (projected) £4,473,000* £8,000,000 £1,041,000 80% 20%
2024 to 2025 £3,151,000 £6,500,000 £745,432 80% 20%
2023 to 2024 £3,151,000 £4,000,000 £1,153,392 65% 35%
2022 to 2023 £3,151,000 £10,000,000 £1,121,663 70% 30%
2021 to 2022 £2,919,000 £10,000,000 £791,121 70% 30%

*£181,000 of this funding comes with conditions that we must meet. On top of that, there's an extra £237,000 given to help develop local transport.

The DfT provides capital funding. You can find out more about this online.

More information on spending

We use our funding in a number of ways:

DfT Capital Grant funding

This is used for work on potholes. We now repair all potholes with a permanent fix to increase how long they last.

The following table shows the estimated number of potholes we have fixed over the years.

Use the first column for financial year, moving right for the estimated number of pot holes filled.
Financial Year Estimate of the number of potholes filled
2024/25 1278
2023/24 1822
2022/23 1447
2021/22 3277 *
2020/21 3469 *

*Includes totals from a targeted pothole programme 'Find and Fix':

We estimate a further 2000 potholes will be fixed this year.

The funding also covers

  • road safety
  • street lighting
  • structures
  • network/junction improvements
  • traffic signals
  • bus infrastructure works

The main capital budget

This relates to our Highway Improvement programme for road and pavement schemes, which we are currently in year 2 of a 5 year programme.

We estimate that in the coming year, resurfacing will include:

  • 8km of road
  • over 15km of pavement

This follows last year's figures of:

  • 6km of roads
  • 11km of pavement

Additional year to year capital budgets

The following examples are not included in the reported spending figures:

  • car park improvements
  • a junction protection programme
  • traffic sign improvements
  • and more

Revenue funding

This concentrates mainly on reported defects and issues:

And covers:

  • emergency 2-hour responses
  • temporary pothole repairs
  • footway defects
  • poor condition signage replacement
  • and more

It will also cover the gully (drains on the road) emptying programme. For now, our current contractor is covering the service until it's added into the new highways contract from April 2026.

Preventative measures and improved efficiency

We focus mostly on preventative maintenance. Our estimated percentage figures clearly show this. In addition to investing heavily in improving our roads, we're now permanently fixing all potholes that meet our repair standards. Because of the risk of carrying out works on some of our busier roads, we may at times, do temporary fixes. These will be followed up with a permanent repair.

We are also working to make our processes more efficient. Recent examples include:

Replacing signage

We now store information on our road signs that are not considered a safety risk. We pass this information to our contractor as a batch of work to complete. This is a more cost-effective option than visiting and replacing each sign one by one.

Disabled parking bays

Following an ongoing review, so far we have freed up 40 spaces that were not being used. Residents can now use them.

We now approve and install up to 50 new disabled parking bays per year. This:

  • makes sure that they are given to those who need them most
  • allows the work to be completed in batches, leading to savings

We believe that we are one of the best authorities in the UK in terms of inspecting reported issues (including potholes). We inspect all reported issues made through MySouthend, on all roads, either:

  • within 24 hours
  • the next working day

Even though the statistics suggest a decrease in activity, we are actually doing more. In the past only temporary fixes to potholes were completed. This led to further visits to the same location and higher repair numbers. Now that we are permanently fixing potholes, return visits are less likely to be needed. By permanently fixing potholes, we believe we are:

  • working in a much more proactive way
  • delivering better value for money

In addition, the numbers only include reports that were specifically labelled as potholes. They don't count works where several potholes were filled at the same time.

Go to top