Highway works and activity permissions

Application Fees and Timeframes

The following table sets out the application fees and the minimum required notice periods for each type of application. Longer notice periods may be required if traffic management, road closures, or complex assessments are involved.

Category Application Fees Application Timescales
Street Works Permit
(Utility works, traffic control, excavation)
N/A

10 working days (major works)

3 working days (standard)

2 hours (emergency)

Section 50 Street Works Licence
(Private excavation in highway)

£300.00

28 calendar days minimum

(3 months required for complex works
Highway Licence for Temporary Obstructions
(Crane, hoarding, scaffolding, building materials)

Hoarding, scaffolding, temporary disturbance are all £280

Crane - £300

28 calendar days

90 days if works exceed 10 working days

Highway Licence for Skip Skip - £160 Skips 10 days
Highway Permit for Special Events
(Parades, stages, structures for events)
Falls under temporary disturbance of £280 6–8 weeks prior to event
Temporary Traffic Regulation Order (TTRO)
(Road closures, lane restrictions, diversions
£1,900

12 weeks (Standard TTRO)

Up to 6 weeks (Emergency TTRO)
Go to top